Execution: Supply and implementation of the telecommunications network for the Al-Masafi Intersection Overpass site. The project included 5 km of excavation and the construction of 58.2 km of network paths using Open-cut excavation and Directional Drilling (Trenchless) technologies to provide the required fiber optic capacity.
The scope of work involved managing utility conflict resolution between legacy telecommunications networks and bridge construction works, ensuring a seamless operational environment within the Traffic Congestion Relief Projects initiative. The project was supervised by the Al-Karkh Communications Directorate.
Partnership: Executed in partnership with Al-Bo’ad Al-Rabi’a (Fourth Dimension) Company and the Ministry of Construction, Housing, and Public Municipalities (Roads and Bridges).