Execution: Supply and implementation of the telecommunications network for the Um Al-Khanazeer and Al-A'aras Island Overpass site. The project involved 5.9 km of excavation and the construction of 70 km of network paths using Open-cut excavation and Directional Drilling (Trenchless) technologies to provide the required fiber optic capacity.
The scope included managing utility conflict resolution between legacy telecommunications infrastructure and bridge construction works, ensuring a seamless workflow within the Traffic Congestion Relief Projects initiative. The work was carried out under the supervision of the Al-Karkh Communications Directorate.
Partnership: Executed in partnership with STRACO (Lebanon) and the Ministry of Construction, Housing, and Public Municipalities (Roads and Bridges).