Execution: Supply and implementation of the telecommunications network for the Aden and Sana'a Squares site. the project involved 4.5 km of excavation and the construction of 54 km of network paths using Open-cut excavation and Directional Drilling (Trenchless) technologies to provide the required fiber optic capacity.
A key component of the project was managing the utility relocation and conflict resolution between legacy telecommunications networks and the bridge construction works, ensuring a seamless workflow within the Traffic Congestion Relief Projects package. The work was conducted under the supervision of the Al-Karkh Communications Directorate.
Partnership: Executed in partnership with Ghaddaq Al-Tabeea Company and the Ministry of Construction, Housing, and Public Municipalities (Roads and Bridges).